Question: The network for a project is shown below. Activity times, in days, are indicated by the figure that appears under each activity. 3 2 4

The network for a project is shown below.

The network for a project is shown below. Activity times, in days, are indicated by the figure that appears under each activity. 3 2 4 9 6 3 1 3 4 4 8 7 9 8 5 5 5 1 3 7 10 (i) Analyse the network to determine the earliest and latest event times and the minimum project duration. Indicate the critical path for the project