Question: The optimistic, pessimistic and most likely times for a project activity are 2.9. and 10 respectively. The expected duration of the activity is: Select one:

The optimistic, pessimistic and most likely times
The optimistic, pessimistic and most likely times for a project activity are 2.9. and 10 respectively. The expected duration of the activity is: Select one: O a. 5.5 b. 75 OC. 8.5 d. 11.5