Question: The overall average on a process you are attempting to monitor is 5 5 . 0 units. The process population standard deviation is 1 .

The overall average on a process you are attempting to monitor is 55.0 units. The process population standard deviation is 1.84. Sample size is given to be 4.
a) Determine the 3-sigma x-chart control limits.
Upper Control Limit (UCL?bar())= units (round your response to two decimal places).
Lower Control Limit (LCLx)= units (round your response to two decimal places).
b) Now determine the 2-sigma x-chart control limits.
Upper Control Limit (UCL?bar())= units (round your response to two decimal places).
Lower Control Limit (LCLx)= units (round your response to two decimal places).
How do the control limits change?
A. The control limits are tighter for the 2-sigma x-chart than for the 3-sigma x-chart.
B. The control limits are tighter for the 3-sigma x-chart than for the 2-sigma x-chart.
C. The control limits for the 2-sigma x-chart and for the 3-sigma x-chart are the same.
 The overall average on a process you are attempting to monitor

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!