Question: The overall project is considered to be the first level of the WBS . All of the following methods can be used to organize the
The overall project is considered to be the first level of the WBS All of the following methods can be used to organize the second level of the WBS EXCEPT:
a Organized by project phase.
b Organized by activities and tasks
c Organized by design components deliverables.
d Organized by work function. subproject