Question: The PM has gone to his human resource manager because he has not received all of the resources required. Ensuring resource availability is the part
The PM has gone to his human resource manager because he has not received all of the resources required. Ensuring resource availability is the part of which process group?
Group of answer choices
Planning process group
Executing process group
Initiating process group
Monitoring and controlling process group