Question: The precedence diagramming method (PDM) is: A. * A technique in which activities are represented by nodes and are graphically linked by one or more
The precedence diagramming method (PDM) is:
A. * A technique in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
B. A method that uses a probabilistic approach to scheduling project activities.
C. A time-phased graphical representation of the arrow diagramming method (ADM), and shows durations of project activities as well as their dependencies.
D. More accurate than the critical path method for scheduling when there are uncertainties about the durations of project activities.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts