Question: The production process in a cookie factory is shown below. There are four tasks performed in separate stations: i) mixing, ii) shaping, iii) baking, and
The production process in a cookie factory is shown below. There are four tasks performed in separate stations: i) mixing, ii) shaping, iii) baking, and iv) packaging. Each cookie needs to go through only one of the two of shaping machines and only one of the three baking ovens. Picture1.png What is the throughput time? What is the bottleneck time? If the factory operates 16 hours per day, 6 days per week, what is the weekly capacity of this cookie factory? The owner is considering to upgrade some equipment to replace one of the existing operations. Which operation should be considered first?
- What is the throughput time?
- What is the bottleneck time?
- If the factory operates 16 hours per day, 6 days per week, what is the weekly capacity of this cookie factory?
- The owner is considering to upgrade some equipment to replace one of the existing operations. Which operation should be considered first?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts