Question: The program evaluation and review technique (PERT) is an _____ network analysis technique used to estimate a project's duration when individual activity duration estimates are

The program evaluation and review technique (PERT) is an _____ network analysis technique used to estimate a project's duration when individual activity duration estimates are highly uncertain. milestone eventoriented illogical relational

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!