Question: The program evaluation and review technique (PERT) is an _____ network analysis technique used to estimate a project's duration when individual activity duration estimates are

  1. The program evaluation and review technique (PERT) is an _____ network analysis technique used to estimate a project's duration when individual activity duration estimates are highly uncertain.

    A

    milestone

    B

    eventoriented

    C

    illogical

    D

    relational