Question: p . 3 ( 3 ) A project was planned using PERT. Its expected completion time was determined to be 6 4 days. The variance

p.3
(3) A project was planned using PERT. Its expected completion time was determined to be 64 days. The variance of the critical path is 26. What is the probability the project will be completed within 59 days (5 decimal places)?
Let x= the project completion time.
Please show how you use the Normal Curve Tabje to obtain your answer in the space below.