Question: The short - term scheduling activity called loading: Part 2 A . assigns jobs to work centers B . assigns workers to machines. C .
The shortterm scheduling activity called "loading":
Part
A
assigns jobs to work centers
B
assigns workers to machines.
C
specifies the order in which jobs should be done at each center..
Dassigns workers to jobs.
E
assigns dates to specific jobs or operations steps.