Question: The short - term scheduling activity called loading: Select one: a . assigns workers to jobs. b . assigns dates to specific jobs or operations
The shortterm scheduling activity called "loading":
Select one:
a assigns workers to jobs.
b assigns dates to specific jobs or operations steps.
c assigns jobs to work centers
d assigns workers to machines.
e specifies the order in which jobs should be done at each center.