Question: The snapback timing method was used in a direct time study of a task that includes a machine cycle. Elements A , B , C

The snapback timing method was used in a direct time study of a task that includes a machine cycle. Elements A, B, C and D are performed by the operator, and element M is a machine semi- automatic cycle. Element B is an internal element performed simultaneously with element M, and element D is an irregular element performed once every 15 cycles. Observed times and performance ratings are given in table below. The PFD allowance factor is 18% and the machine allowance is 20%. Determine (a) the normal time and (b) the standard time of the work cycle using an allowance factor of 15%