Question: The snapback timing method was used in a direct time study of task includes a machine cycle. Elements a, b, c, and d are performed

The snapback timing method was used in a direct time study of task includes a machine cycle. Elements a, b, c, and d are performed by the operator and element m is a machine semiautomatic cycle. Element b is an internal element performed simultaneously with element m. Element d is an irregular element performed every 12 cycles. Apfd = 0.1. Am = 0.15

Work element _____ a b c d __

Observed time, manual, 0.34 0.75 0.55 0.65

Performance rating 110% 90% 95% 100%

Machine element m

Observed time, machine (idle) 1.5 (idle) (idle)

Select correct answer from below.

  1. 1.045

  2. 1.725

  3. 2.77 min

  4. 2.45 min

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!