Question: The snapback timing method was used in a direct time study of task includes a machine cycle. Elements a, b, c, and d are performed
The snapback timing method was used in a direct time study of task includes a machine cycle. Elements a, b, c, and d are performed by the operator and element m is a machine semiautomatic cycle. Element b is an internal element performed simultaneously with element m. Element d is an irregular element performed every 12 cycles. Apfd = 0.1. Am = 0.15
Work element _____ a b c d __
Observed time, manual, 0.34 0.75 0.55 0.65
Performance rating 110% 90% 95% 100%
Machine element m
Observed time, machine (idle) 1.5 (idle) (idle)
Select correct answer from below.
-
1.045
-
1.725
-
2.77 min
-
2.45 min
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts