Question: The Table below represents the tasks for a project. The labor column is in hours of effort. The labor rate is $ 8 0 /

The Table below represents the tasks for a project. The labor column is in hours of effort. The labor
rate is $80/hour. The purchase column is from suppliers quotes. The start and finish columns
represent the planned start and finish date for each activity. Create a project budget and determine
how much money is planned to be spent in each month.
# Labor Purchase Start Finish
Task 130 hours Feb 15 Feb 28
Task 280 hours Feb 20 Mar 1
Task 350 hours Mar 2 Mar 14
Task 410 hours $100,000 Mar 15 Mar 31
Task 5100 hours Mar 15 Mar 31
Task 645 hours $350,000 Mar 15 Mar 31
Task 760 hours Apr 1 Apr 19
Task 8210 hours Apr 20 Apr 27
Task 9140 hours Apr 10 May 2
Task 1090 hours $50,000 May 3 May 9
Task 11160 hours May 10 May 22
Task 12240 hours May 10 May 29
Task 13200 hours May 10 Jun 7
Task 14310 hours May 10 Jun 21
Task 15270 hours Jun 22 Jun 29
Task 16375 hours Jun 30 Jul 14
Task 1760 hours $75,000 Jul 15 Jul 31
Task 18150 hours Jul 15 Jul 31
Task 19120 hours Aug 1 Aug 9
Task 2080 hours Aug 10 Aug 25

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!