Question: The value stream map in Figure 7 . 1 shows that there are 3 problematic processes involved in processing a washing machine, cutting, bending and

The value stream map in Figure 7.1 shows that there are 3 problematic processes involved in processing a washing machine, cutting, bending and punching. Information regarding the availabilities, setup times and processing times at each of these 3 processes is shown in Table 7.1.
Table 7.1 processing and setup times for the washing machines at Ormonde Inc.
Plant
Availability (%)
Setup time in minutes
Cycle time in seconds
Cutting
100
3
120
Bending
99
5
250
Punching
100
0
140
Given that the daily demand is 550 units with a batch size of 20 units. Workers at Ormonde Inc, work 3,8-hour shifts per day each with a break of 45 minutes.
Calculate:
The takt time in seconds 152.18
The production lead time in days Blank 2
The total processing time in seconds 510
The capacity of the work cell Blank 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!