Question: The work breakdown structure for building a house (levels 1 and 2) is shown below: Level 1 HOUSE Level 2 ( Masonry Carpentry Plumbing Site

The work breakdown structure for building a house

The work breakdown structure for building a house (levels 1 and 2) is shown below: Level 1 HOUSE Level 2 ( Masonry Carpentry Plumbing Site Preparation Finishing a) To provide more detail to the WBS, for the plumbing activity the appropriate next level activities could be: O A. Irrigation System OB. Toilets and Sinks OC. Underground Pipes OD. All of the above