Question: The work breakdown structure for building a house (levels 1 and 2) is shown below: (a) Add two level-3 activities to each of the level-2

The work breakdown structure for building a house (levels 1 and 2) is shown below:

The work breakdown structure for building a house (levels 1

(a) Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS.
(b) Select one of your level-3 activities and add two level-4 activities belowit.

Level 1 House Level 2 Ste MaeonyCarpnlryPlumbg Finishing

Step by Step Solution

3.43 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Some possible Level 3a and Level 4b activities for the ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

256-B-M-L-O-M (1375).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!