Question: The work cycle time components in a worker - machine system are; 1 - External work elements Total Normal Time: 0 . 4 2 min

The work cycle time components in a worker-machine system are; 1- External work elements Total Normal Time: 0.42min
2- Machine processing time: 1.12min
3- Internal work elements Total Normal Time: 1.04 min
According to this data;
a) Calculate the Standard Time using the tolerance factor of 15% for the worker and 30% for the machine.
b) How many parts are produced per day (in an 8-hour shift) based on the eight-hour standard performance?
c) If zero tolerance is accepted for the machine, what will be the daily production amount?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!