Question: Consider the following project network with normal activity times (in weeks) associated with each node. By adding more resources, some activities may be completed
Consider the following project network with normal activity times (in weeks) associated with each node. By adding more resources, some activities may be completed in less than their normal time. The crash times and associated costs per week are given in the table below. B Reference: In-Class Paper Manufacturing Project The critical path is A.A-C-F-H B.A-C-E-G-H C. B-D-G-H D.A-C-E-G-H and B-D-G-H OE. none of the above Activity Crash Time (Weeks) Crash Cost / Week (5) A 750 BCDEFGH 1 1 3 2 2 2 1 2,000 1,000 1,000 1,000 500 1,500 3,000
Step by Step Solution
There are 3 Steps involved in it
Ans d G E and D Project crashing is when we shorten the duration of a project b... View full answer
Get step-by-step solutions from verified subject matter experts
