Question: There are five activities on a project's critical path and they have standard deviations of 2, 2, 5, 6, 6 days. The standard deviation (in

There are five activities on a project's critical
There are five activities on a project's critical
There are five activities on a project's critical path and they have standard deviations of 2, 2, 5, 6, 6 days. The standard deviation (in days) of the critical path is: O A. 9.8 OB. 4.6 OC.7.8 OD. 10.6 E. 102 OF 88 2.75 points A manufacturer maintains an inventory of needles. Inventory consumption is constant at 1600 needles per day and lead time for new needles is constant at four days. If the manufacturer wishes to maintain a safety stock of 800 needles, what should its reorder point be? OA 6000 OB. 4800 OC 6600 OD.7200 E 5000 OF 5400

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!