Question: There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J- K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 70
There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-JK-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 70 hours. The maximum possible reduction in the project duration will be: a. 350 hours b. 980 hours c. 490 hour d. 280 hours e. Insufficient information