Question: There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H- J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 123

There are five critical paths in a network.

There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H- J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 123 hours. The maximum possible reduction in the project duration will be: O a. 861 hour Ob 492 hours Oc615 hours Od 1722 hours e. Insufficient information