Question: 38 There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 79

38 There are five critical paths in a network.
38 There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 79 hours. The maximum possible reduction in the project duration will be ut of O a. 316 hours uestion Ob Insufficient information O c. 395 hours Od 1106 hours O e 553 hour