Question: Question 30 There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by

Question 30 There are five critical paths in a

Question 30 There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 77 hours. The maximum possible reduction in the project duration will be: Not yet answered a. 1078 hours Marked out of O b. 308 hours 1.00 C. Insufficient information Flag question d. 385 hours e. 539 hour