Question: There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 88 hours.
There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y-E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 88 hours. The maximum possible reduction in the project duration will be:
a. 352 hours b. Insufficient information c. 1232 hours d. 440 hours e. 616 hour