Question: There are five jobs A, B, C, D and E having processing times of 7, 5, 7, 4 and 3 days respectively on first workcenter
There are five jobs A, B, C, D and E having processing times of 7, 5, 7, 4 and 3 days respectively on first workcenter and 2, 6, 9, 4 and 7 days respectively on second workcenter. In order to schedule them on the two workcenters, which job will be sequenced as the first one?
A
B
C
D
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts