Question: There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 7 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $540, E is $555 and all other activities is : $135 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1350 per week, E is $1620 per week and for all other activities is $270 per activity per week. You have a maximum crashing budget of $3380. The maximum possible reduction in the project duration will be:
a.
6 weeks
b.
2 week
c.
3 weeks
d.
4 weeks
e.
5 weeks