Question: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 131 hours. The
There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E.
Each activity in this network can be crashed by 131 hours. The maximum possible reduction in the project duration will be: a. Insufficient information b. 524 hours c. 786 hour d. 655 hours e. 1703 hours