Question: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 38 hours. The
There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 38 hours. The maximum possible reduction in the project duration will be:
a. 190 hours
b. 152 hours
c. 228 hour
d. 494 hours
e. Insufficient information