There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 113 hours. The maximum possible reduction in the project duration will be:

a. 678 hour

b. 1469 hours

c. Insufficient information

d. 452 hours

e. 565 hours