Question: There are two resources in a serial process. The yield of the first resource is 9 0 % and the yield of the second resource

There are two resources in a serial process. The yield of the first resource is 90% and the yield of the second resource is 75%. The first resources capacity is 15 units per hour. The second resources capacity is 10 units per hour. Demand on this process is 12 units per hour. What is the implied utilization (%) of the second resource?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock