Question: This problem is designed to demonstrate your basic understanding of Network Scheduling and the use of a software tool like MS Project. A new application

This problem is designed to demonstrate your basic understanding of Network Scheduling and the use of a software tool like MS Project.

A new application development project at ACME7365 Inc. consists of the following activities:

Activity

Predecessor

Estimated Duration (Days)

A

3

B

4

C

4

D

A

3

E

D

4

F

E

3

G

F

4

H

F

5

I

G, H

6

J

G

3

K

H

4

L

I, K

5

M

J

2

  1. Draw (sketch) this network manually as a PDM network using the proper network conventions.
  2. Display the network diagram using a software tool such as Microsoft Project.
  3. Indicate the critical path and the total project duration?
  4. Which activity has the largest slack? How much?
  5. Crash the project by 3 days and re-identify the critical path?
  6. If you delete activities K and M, what is the critical path? How many days do you save? Can you still crash the project by 3 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!