Question: This problem is designed to demonstrate your basic understanding of Network Scheduling and the use of a software tool like MS Project. A new application
This problem is designed to demonstrate your basic understanding of Network Scheduling and the use of a software tool like MS Project.
A new application development project at ACME7365 Inc. consists of the following activities:
| Activity | Predecessor | Estimated Duration (Days) |
| A |
| 3 |
| B |
| 4 |
| C |
| 4 |
| D | A | 3 |
| E | D | 4 |
| F | E | 3 |
| G | F | 4 |
| H | F | 5 |
| I | G, H | 6 |
| J | G | 3 |
| K | H | 4 |
| L | I, K | 5 |
| M | J | 2 |
- Draw (sketch) this network manually as a PDM network using the proper network conventions.
- Display the network diagram using a software tool such as Microsoft Project.
- Indicate the critical path and the total project duration?
- Which activity has the largest slack? How much?
- Crash the project by 3 days and re-identify the critical path?
- If you delete activities K and M, what is the critical path? How many days do you save? Can you still crash the project by 3 days?