Question: This project has 4 paths, how long will it take at a minimum? ABEFGJ 10 days ABDGJ 8 days ACDGJ 9 days ACHIJ 9 days
This project has 4 paths, how long will it take at a minimum?
ABEFGJ 10 days
ABDGJ 8 days
ACDGJ 9 days
ACHIJ 9 days