Question: This project has 4 paths, how long will it take at a minimum? ABEFGJ 10 days ABDGJ 8 days ACDGJ 9 days ACHIJ 9 days

This project has 4 paths, how long will it take at a minimum?

ABEFGJ 10 days

ABDGJ 8 days

ACDGJ 9 days

ACHIJ 9 days

8 days

9 days

none of the answers are correct

10 days