Question: Time Required in Weeks Activity Preceding Optimistic Most likely Pessimistic A 28 32 36 B 22 28 32 A 26 36 46 D B 14

Time Required in Weeks Activity Preceding

Time Required in Weeks Activity Preceding

Time Required in Weeks Activity Preceding Optimistic Most likely Pessimistic A 28 32 36 B 22 28 32 A 26 36 46 D B 14 16 18 E B 32 32 32 F B 40 52 74 G 12 16 24 H E,G 16 20 26 I E,G 26 34 42 J CF 12 16 30 D a. Construct the project network diagram and attach it at the end of the question below!. (2-Marks) b. Calculate (ES),(EF),(LS), (LF) and Slack time for each activity. (3-Marks) Tasks----- Early Start ----- Early Finish ----- Late Start ----- Late Finish ----- Slack A B Uw LUI - J

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!