Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 21 33 57 B 1

TIMES (days)

Activity

Start Node

Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A

1

2

21

33

57

B

1

3

17

23

41

C

2

5

13

25

61

D

3

4

28

40

76

E

4

5

16

40

64

Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 35 Standard Deviation = 6 Activity Bte =

Standard Deviation =

Activity Cte =

Standard Deviation =

Activity Dte =

Standard Deviation =

Activity Ete =

Standard Deviation = 8 Path 1 2 5 Mean Time =

Standard Deviation =10 Path 1 3 4 5 Mean Time =

Standard Deviation =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!