Question: Question 2 options: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 20 26
Question 2 options:
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 20 | 26 | 38 |
| B | 1 | 3 | 23 | 29 | 47 |
| C | 2 | 5 | 12 | 24 | 36 |
| D | 3 | 4 | 29 | 41 | 53 |
| E | 4 | 5 | 12 | 33 | 54 |
Given the Activity on Arrow Diagram and the data found in the table above, c
Calculate each of the following values: Activity Ate = 27 Standard Deviation = 3
Activity Bte = Standard Deviation =
Activity Cte = Standard Deviation =
Activity Dte = Standard Deviation =
Activity Ete = Standard Deviation = 7 Path 1 2 5 Mean Time = Standard Deviation =5 Path 1 3 4 5 Mean Time =
Standard Deviation =