Question: Question 2 options: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 29 35
Question 2 options:
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 29 | 35 | 47 |
| B | 1 | 3 | 23 | 26 | 35 |
| C | 2 | 5 | 17 | 29 | 41 |
| D | 3 | 4 | 27 | 45 | 63 |
| E | 4 | 5 | 12 | 39 | 66 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 36 Standard Deviation = 3 Activity Bte =
Standard Deviation =
Activity Cte =
Standard Deviation =
Activity Dte =
Standard Deviation =
Activity Ete =
Standard Deviation = 9 Path 1 2 5 Mean Time =
Standard Deviation =5 Path 1 3 4 5 Mean Time =
Standard Deviation =