Question: To allocate resources for resource-constrained projects, project managers may perform the following activities EXCEPT: Constrained to level within available slack times Prioritizing activities based on

To allocate resources for resource-constrained projects, project managers may perform the following activities EXCEPT: Constrained to level within available slack times Prioritizing activities based on slack times Delaying activities with slack times Delaying activities without slack times Applying the parallel method in scheduling