Question: To reduce the duration of a project using CPM , it is necessary to make a reduction on the activity with: the largest cost slope
To reduce the duration of a project using CPM it is necessary to make a reduction on the activity with:
the largest cost slope not on the CP
the smallest cost slope not on the CP
the largest cost slope on the critical path CP
the smallest cost slope on the CP