Question: To reduce the duration of a project using CPM , it is necessary to make a reduction on the activity with: the largest cost slope

To reduce the duration of a project using CPM, it is necessary to make a reduction on the activity with:
the largest cost slope not on the CP
the smallest cost slope not on the CP
the largest cost slope on the critical path (CP)
the smallest cost slope on the CP

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!