Question: true or false 1) In a network diagram, the smallest unit of work effort consuming both time and resources that a project manager can schedule

true or false
true or false 1) In a network diagram, the
1) In a network diagram, the smallest unit of work effort consuming both time and resources that a project manager can schedule and control is called an activity. 1) 2) The probability of finishing a project earlier than the time of critical path is zero. 2) 3) ) 3) Input measures of capacity are inherently more accurate than output measures of capacity