Question: True or False In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have
True or False
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.