Question: Two job types are processed on a two-station flow line. The first job type has processing times of 7 minutes on the first station
Two job types are processed on a two-station flow line. The first job type has processing times of 7 minutes on the first station and 5 minutes on the second. The second job type has processing times of 9 minutes on the first station and 12 minutes on the second. a. Assume the two job types have the same arrival rate. What is the raw processing time, the bottleneck rate, the critical WIP and capacity of the line? b. What job mix balances the line? What is the percent improvement in capacity from the balanced line?
Step by Step Solution
3.48 Rating (161 Votes )
There are 3 Steps involved in it
The question presents a twostation flow line with two job types which have different processing times for each station We need to calculate several operational metrics for this system Lets tackle part ... View full answer