Question: Use Microsoft Project Online to create a new project with the following tasks and durations. Do a critical path method (CPM) analysis. Task Predecessor Duration
Use Microsoft Project Online to create a new project with the following tasks and durations. Do a critical path method (CPM) analysis.
| Task | Predecessor | Duration in days |
| A | None | 5 |
| B | None | 4 |
| C | A | 3 |
| D | A | 4 |
| E | A | 6 |
| F | B,C | 4 |
| G | D | 5 |
| H | D,E | 6 |
| I | F | 6 |
| J | G,H | 4 |
Change the view to Task Schedule from Task Summary to note the Early Start/Finish and Late Start/Finish, and Free/Total Slack. In the Gantt Chart (on the right), mark the critical tasks and the Critical Path.
Mention the critical path and shortest total project completion time.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts