Question: Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table. Construct a

Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.

  1. Construct a labeled network diagram (include duration, early/late times) on paper then insert the image below the table.
  2. Calculate and enter the free slack and total slack for each task in the table.
  3. List all paths with durations and identify the critical path.


Task

Predecessor

a

m

b

Normal duration

Free Slack

Total Slack

A

---

3

4

7




B

---

4

6

10




C

A, B

5

8

11




D

A

8

9

12




E

C

7

8

9





Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Computer Network Questions!