Question: Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table. Construct a
Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.
- Construct a labeled network diagram (include duration, early/late times) on paper then insert the image below the table.
- Calculate and enter the free slack and total slack for each task in the table.
- List all paths with durations and identify the critical path.
Task | Predecessor | a | m | b | Normal duration | Free Slack | Total Slack |
A | --- | 3 | 4 | 7 | |||
B | --- | 4 | 6 | 10 | |||
C | A, B | 5 | 8 | 11 | |||
D | A | 8 | 9 | 12 | |||
E | C | 7 | 8 | 9 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
