Question: Use the activity table below. Find theproject completion time. What is the total cost for all tasks on the critical path only? Activity Predecessor Time(days)
Use the activity table below. Find theproject completion time. What is the total cost for all tasks on the critical path only?
Activity Predecessor Time(days) Cost
1 - 3 300
2 1 2 350
3 2 10 1250
4 2 6 880
5 3 5 675
6 4,5 3 325