Question: Use the earned value table for Project Makeready to calculate its cost performance index at the end of July. Activity Jan Feb Mar Apr May

Use the earned value table for Project Makeready

Use the earned value table for Project Makeready to calculate its cost performance index at the end of July. Activity Jan Feb Mar Apr May June July Plan Complete Install fixtures 325 250 575 100% Refinish floors 550 85 635 100% Replace doors 350 275 625 100% Complete tiling 1,200 565 1,765 80% Install back door 875 225 1,100 70% Landscaping 200 350 550 25% Monthly Plan 325 800 435 1,475 1,440 425 350 5,250 Monthly Act 550 550 550 1,100 1,650 550 1,100