Question: Use the following Activity on Node (AON) network to answer the following questions. 1. Task B's earliest start time is _____? 2. Task K's early
Use the following Activity on Node (AON) network to answer the following questions.

1. Task B's earliest start time is _____?
2. Task K's early finish time is ________ and task K's late finish time is_______?
3. The project's expected finish time is _______?
4. Task D's slack time is _____?
5. Task i's slack time is ______?
b 6 4. ODOO g 8 d 8 a 10 h 6 e 15 k 10 i 3 f 4 + j 9Step by Step Solution