Question: Use the following Activity on Node (AON) network to answer the following questions. 1. Task B's earliest start time is _____? 2. Task K's early

Use the following Activity on Node (AON) network to answer the following questions.

Use the following Activity on Node (AON) network

1. Task B's earliest start time is _____?

2. Task K's early finish time is ________ and task K's late finish time is_______?

3. The project's expected finish time is _______?

4. Task D's slack time is _____?

5. Task i's slack time is ______?

b 6 4. ODOO g 8 d 8 a 10 h 6 e 15 k 10 i 3 f 4 + j 9