Question: Using the table below, answer the proceeding questions. Activity Preceding Activity Optimistic Duration (Days) Most Likely Duration (Days) Pessimistic Duration (Days) Crash Cost per Day

Using the table below, answer the proceeding questions.

Activity

Preceding Activity

Optimistic Duration (Days)

Most Likely Duration (Days)

Pessimistic Duration (Days)

Crash Cost per Day ($)

Max Crash (Days)

A

-

2

4

5

-

-

B

-

2

4

5

100

3

C

A, B

1

2

4

400

1

D

C

4

6

9

150

1

E

C

1

2

5

300

2

F

E

2

4

5

300

2

G

D

1

3

6

200

1

H

F, G

3

4

5

-

-

a. Using the activity-on-node, AON, method of depicting a project, construct a network diagram showing the relationships defined in the table. Use MS Word graphics to produce the diagram.

b. What is the critical path or paths of the project? c. What is the probabilistic duration of the project? Use two decimal places for each iterative calculation.

d. If the project manager requires that the project duration be reduced by one day, which activity shall be crashed?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!