Question: Using the information from the following table, create an AON network activity diagram. a. Calculate each activity TE (rounding to the nearest integer); the total
Using the information from the following table, create an AON network activity diagram.
a. Calculate each activity TE (rounding to the nearest integer); the total duration of the project; its early start, early finish, late start and late finish times; and slack for each activity. Finally, show the project’s critical path.
.png)
b. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the project’s schedule? Has the duration changed? Is there a new critical path? Show your conclusions.
Step by Step Solution
There are 3 Steps involved in it
a Totalduration of the project is 82 days Criticalpath ABDGIK b Be... View full answer